The Farm Timeline

With voter approval of The Farm project, many are anxious to see the property cleaned up, some looking forward to glass of wine at “The Social”, and others see it as an opportunity to move into a new home. We asked Kevin McNamara for a timeline and here’s how he foresees the project moving forward:

Winter 2020

  • Cleanup the street frontage along Espola Road

  • Mow the weeds on the golf course

  • Trim dead trees

  • Remove the driving range netting

  • Repair the temporary fence around the property

Spring 2021

  • Close escrow on the property (at that point Michael Schlesinger will no longer be involved)

  • Raze the former club house and old support buildings

Summer 2021

  • Complete the final engineering plans

Fall 2021

  • Secure grading and building permits from the City of Poway

  • Commence grading

Spring 2022

  • Start construction

Summer 2022

  • Model homes completed

Winter 2022

  • First homes ready for occupancy